Construction Works Start at the New Stracathro Hospital, Brechin :: Latest News

17th August 2010

Kilmac have commenced lime stabilisation on the recently awarded groundworks package for the New Hospital at Stracathro, Brechin.

The groundworks package in excess of £3 million includes £30,000m³ bulk earthworks, substructure for the New 6000m² facility and drainage/hard landscaping package.

Works are estimated to take 66 weeks.

Back to Latest News

roadwork_001.jpg
Accreditation
website powered by Blue Square