17th August 2010
Kilmac have commenced lime stabilisation on the recently awarded groundworks package for the New Hospital at Stracathro, Brechin.
The groundworks package in excess of £3 million includes £30,000m³ bulk earthworks, substructure for the New 6000m² facility and drainage/hard landscaping package.
Works are estimated to take 66 weeks.