Aberdeen Causeway

»»»Aberdeen Causeway
Aberdeen Causeway2017-05-16T20:57:35+00:00

Project Outline

Construction of a 7 story student accommodation in Aberdeen City Centre. Kilmac’s scope of works include earthworks, foundations, drainage,  attenuation systems, and hard landscaping.

Project Highlights

  • The building footprint covered almost the entire site, therefore programming the construction phasing was key, particular attention was given to the installation sequence of the foundations.
  • Due to the depth of foundations and adjacent ground levels Kilmac had to carry out extensive underpinning and trench fill operations.
  • Due to the lack of a site storage compound, Kilmac had to carefully plan all deliveries taking cognisance of the limited space whilst ensuring the required materials were available for construction.

Project Info

Client
Robertson Construction

Project Value
£300,000

Start / End Dates
May 2016 / July 2017