Project Outline

We are delighted to have been awarded the Groundworks Package by Andrew Shepherd Construction to assist in the extension and upgrade of Cairnie Loan Recycling Centre in Arbroath. The works involve but are not limited to the re-alignment of boundary fencing, excavation and disposal off site to allow the placement of new concrete hardstanding’s, re-surfacing, additional drainage, construction of new retaining walls and service tracks.

During the works the facility is remaining operational and Kilmac are responsible for all traffic management, as always we are in constant dialogue with all stakeholders to ensure the works are undertaken safely and with as little disruption as possible to the day to day operations.

This is our second project working with Andrew Shepherd in recent months, our first being the new Food & Drink Park located in Inveralmond, Perth.

Project Info

Client
Andrew Shepherd Construction

Contract Value
£138,000.00

Commencement Date
1st May 2017

Contract Duration
12 weeks